Wednesday, May 30, 2012

Week 8

Week 8
         Week 8 lab was really productive for the team for being able to put all members ideas into a final design.  Also it was a great opportunity for the team to test different 2 feet bridge designs that were brainstormed.  We were able to see main weaknesses and strength of each design.  The results from these experimentations will be considered for the design and construction of the final bridge design.
         I had found this engineering design project really interesting and enjoyable.  Each part of the module was has it’s own important significance and has teach me really interesting and important basic knowledge about bridges.  During the first part of the project when we were able to play around with WPBD I was able to see what structures had a successful strength.  Also I was able to play around with the building materials to be able to bring the cost down of the bridge while keeping its strength.  During this process I was able to get a better understanding of what structure designs seem to be more successful.  I learned that triangles do an excellent job distributing forces.  It is important to consider the fact that this are not the only forces a conditions to which a bridge has to survive.  We were then introduced a way to be able to calculate the tension that each member of the bridge.  It is important to mention that each method and program used during this project had their own strengths and limitations.  Finally the most challenging part of this lab was to actually put all of our ideas and knowledge into designing a bridge that would have a good cost vs. strength ratio.  

Tuesday, May 29, 2012

Week 9

Last week during our lab period we were asked to begin our final bridge design. Throughout the period we brainstormed and tested what worked and what didn't work. We constructed two designs that we had in mind, both of these designs were drastically different than our first design, they both involved using more single connector plates rather that the ones that have to be connected to each other to be functional. We implemented these plates by conecting the membranes differently, the memebers were connected on their side rather than their ends. Unfortunately this didn't work as planned, the bridge failed because it twisted and bent sideways. Although these designs didn't perform as we wanted them to we learned more things about how the Knex pieces can be used. As we come closer to the end of the term I can look back and actualy see how much I have learned about how to design a bridge. Many of the things that I took for granted for example the number of connections that were used in the design have a direct effect on how the bridge can support a certain load. I have also learned that the way the members are positioned also affect the distribution of the stresses of each member. The most crucial thing that I learned was how the bridge bent when it was loaded. This helped us decide on putting an extra truss in the middle of the original truss.

Week 9

     In the prior week our group was instructed that the gusset plates were able to become stronger with the increased number of connections. We then constructed a new bridge that partially followed our old design, but used far less amount of materials. The bridge proved to be to week and failed by twisting. The design was altered to strengthen the connections between the two sides of the bridge. This design wasn't able to hold as much weight and failed due to weak gusset plates.
     In the next week we are going to move the support that protects against twisting to the top of the bridge instead of the bottom. We will also test the bridge to see what its max load is.
     Major accomplishments for this week are having a bridge that follows our initial design, but with less materials than what we first tried. The bridge failures are also a promising factor as it shows that the bridge can vertically hold the weight; it just has a tendency to slide and twist on itself.
     The issues that have arisen are that the bridge it structural weak when horizontal forces are put on it. The problem with fixing this issue is that the solutions cause for a weaker bridge in the vertical forces. The best solution will allow for no twisting while at the same time not sacrificing vertical strength of the structure.
     What I have learned from the bridge design process is that everything aspect of design for a real bridge must be considered so catastrophes don't occur and no one is harmed. I learned that all truss designs are built out of triangles as these don't shift as squares and more sided shapes would. The forces on all the member can be broken down to see exactly what forces act on each member. The forces include tension and compression forces. I also learned that the weakest points on a bridge are the connections.

By Robert Weldon

Wednesday, May 23, 2012

Week 8


In the previous Lab we were given the chance to start playing around with online Bridge Design and work on the A3 assignment.  In the next lab we would making analysis and calculations for the angles and triangles been used with Knex.  We hope that the information provided by this analysis will help us improve our design.  We hope to be able to maximize the strength of the bridge and minimize its cost.
Both the hand and online Bridge Design calculations are not sufficient analysis for building a real bridge.  It is important to mention that there was several significant limitations found with online Bridge Design.  These limitations are expressed in A3-Almendariz.   As stated before, there are much more forces and derivable that need to be considered for building a real bridge design.   Unfortunately these calculations are only made for the side part of bridge and the calculations for a third dimension is ignored.  Also in order to build successful bridge we need to consider much more outside factors than the downward force resistance.  We need to consider what materials we would use, in order get a good ratio between price and strength.  Also we need to consider the weather, type of ground, wind forces, etc. from the location where the bridge is going to be built.  There needs to be a further study, calculations and testing to be made before been able to come with a successful real bridge design.  

A3-Almendariz

1.






2.


Member
Force (N)
TAC
22.23
TAB
-31.44
TBC
31.44
TBD
-44.46
TDC
31.42
TDE
-31.44
TCE
22.23

Total Weight

44.45




3.  


4.  Using Online Bridge designer is an easier and faster way to calculate the forces for a bridge design than calculating them manually as before.  Although the program was really versatile for calculations, there were some important restrictions found.  Online Bridge designer had restrictions involving the weight added, the scaling of length of trusts and their angles, and position of nodes.  There was a small window for choosing the load been added, it is limited to multiples of five.  We would not be able to know exactly the length of each trust that we are using and the angle between them.  These restrictions made it difficult to know were was the right position for placing the nodes.  In order to be able to correspond the results from part 1 to bridge design we would need the right scaling for each component and be able know and plug exact numbers for each components.  It is important to note that although online bridge design had it’s restrictions, the calculations given were reasonable close to the calculations done by hand before. 
  5.






While trying to replicate our bridge design in online Bridge design program a big restriction was found.  Online Bridge Designed required relating the numbers of nodes to the number of members.  Our original bridge design had to be altered in order to get it working with the program.  We were forced to take some members out and a node out.  It is for this reason that these calculations are not accurate.

6.  The data provided by the results from the testing of Knex Joints are really useful for the final design.  The results from the testing showed that that the more joint socked we used, it would create a stronger structure.  We are able to know and give an estimate of how much force each connector will be able to resist before it collapses.  We would consider this data for improving our next bridge design by trying to maximize it’s force resistance.    

Week 8

     In the prior week's lab, we learned what the Method of Joints is. Through the Method of Joints we began to construct the tension and compression forces that appear on a given bridge with constraints as to the height, length, and load on the bridge. This analysis helps to show what angles create better triangles that can hold more weight.
     In the coming week our team will begin to analysis the triangles and angles used in our Knex bridge, same with the member lengths. We hope to find that we can cut costs in certain areas, and increase the overall integrity of the Knex bridge.
     The major accomplishment of the week for the team was successfully able to learn and understand the Method of Joints and apply it to the constraint given 2-dimensional bridges and a 2-dimensional version of our team's Knex bridge.
     Issues that may arise in the up coming weeks include unable to find the right members or members combination that increase the strength of our bridge. It may be that our bridge is already built to its full potential and nothing else can be done. It may also be hard to decipher our analysis of our Knex bridge using the method of joints.
     The Method of Joints is not a sufficient form of analysis because it does not account for multiple loads on the bridge in areas other than the middle of the structure. It also does not account for horizontal forces such as wind and rain, which can add to the forces acting on the bridge. It would be a sufficient form of analysis if outside factors and change in the loads could be accounted for. To further analysis the bridge, tension and compression strengths of each member will need to be known to know what their breaking point is. What may help assist in this analysis is a more advanced program than WPBD, but one that measures the same information.

By Robert Weldon

A3-Weldon

 Method of Joints




     The necessary steps for converting the hand analysis that was done to a format that Bridge Designer can use to give you the same results is a method of scaling. Bridge Designer gives you a grid to work on, you can set any number of inches to each square that fits the user. I set each square equal to 2 inches. Doing this made it possible for me to find the correct ratio of distance for all the nodes.
     One problem that we found using Bridge Designer was that it required the user to relate the number of nodes to the number of members used in the bridge design. Our bridge had more members than nodes so we were unable to test our actual design, but a similiar version was used.
     This information about the method of joints greatly helps with the final design of our Knex Bridge. We will be able to see what the angles of the connectors produce in terms of tension and compression of the certain member that is in that location. We can then compare this information to the failure point of each size of Knex to see which piece will be best suited where, while still maintaining the design of the bridge and increasing its integrity.

By Robert Weldon

Tuesday, May 22, 2012

Week 8

During las week's lab we were introduced with a way of analyzing the forces on each part of a truss. This method is called the joint method analysis, this method basically analyzes the force on each junction. Using basic trigonometry the forces of tension and compression can be calculated. We spent the whole lab period doing calculations and figuring out how these forces will help us produce the best design possible for the final project. This week our focus will be to collaborate, and use the joint method analysis to improve on our current design and see how the design changes with the added length.
This method of analysis will be useful but not in all the situation we may encounter. Unfortunately this method of analysis only considers the front part of the truss, ignoring its third dimension. This method is also a very simplistic way of considering how the force acts on the truss. It considers the force to be even at a certain point and fails to consider it coming from more than one point, this will change the results of tension and compression forces. The material which the bridge is constructed is also very important when considering the forces that it will actually support. A detail that will have to be kept in mind is how the actual KNEX react with the forces that are added to them.

A3 - TRUSS ANALYSIS - Hidalgo

1)
Here are my calculations for the forces that are experienced by the members.

2)

Member
Force (N)
AC
22.23
AB
-31.43
BC
31.43
BD
-44.452
DC
31.43
DE
-31.43
CE
22.23

Total Weight

44.452
3)
4) The bridge designer is an easier way of calculating the forces that act on a certain bridge design, compared to part 1 this way is more effective. One of the restrictions of doing it with this software is that the load added is limited to multiples of 5 so to convert part 1 to this type of analysis a conversion had to be made not only to the load but also the design. Using similar triangles the scaling of the truss in part 1 to this analysis is easy by maintaing the angles between the triangles.

5)
One of the problems with this bridge designer is that it requieres the design to relate the number of nodes to the number of members so in the case of this truss it some of the design had to be taken out of the design so that the program would work. This analysis isn't accurate since the design isn't complete.

6) The results that are shown will be useful for our final design because we can now estimate how much force each of the connectors can resist before the member is forced out of the connectors socket. When designing the bridge its obvious that when more of the joint's sockets are being used, there will have to be a greater force to disconnect the member from the connector's socket. With this knowledge more improvements can be made to our design by changing the direction in which the members are oriented.


Tuesday, May 15, 2012

Week 7

     In the prior week our group tested the bridge that we thought would be most successful. This bridge had an arch design to it. We learned that the arch didn't help at all and in the next test wouldn't be allowed. We had another bridge already built and we able to test it even though we submitted the results for the first bridge. The second bridge was able to hold double the first.
     In the coming week my group hopes that we will be able to analyze the forces acting on the bridge and modify it in such a way that will redistribute the forces in such a way to give the bridge more structural strength. We are also going to see if we can cut costs anywhere without taking away from the structural integrity of the bridge.
     Major accomplishments of the week include the realization that an arch is useless in our design. We also discovered that our second design had a relatively high cost to weight ratio, this gives us hope that we can modify it to make it even better.
     Issues that may occur is that the bridge is already built to its highest strength and won't be able to be improved.
     Numbers I believe would be helpful for my bridge design process would be at what weight or force the gusset plates fail at. Knowing this may help my group to redesign our bridge with fewer gusset plates or more depending on the information we gain. It also be helpful to know how certain triangles break up the force acting on them and how they redistribute it across the bridge or themselves. I know that the force of gravity acting on the bridge is the most essential force that must be considered; the mass of the bridge and the bucket of sand is the necessary force to consider in F=mg. Knowing this you can break the forces up on the triangle and see how it redistributes them in the x and y directions.

Robert Weldon - Group 10

Week 7


Week 7
            During last week lab each team was given the chance to test our 2’ bridges in a competition scenario.  Our team was able to test two bridges designed by two group members.  The two designs were really different from each other.  One of them had an arch shape while the other one had a common trust bridge design.  Originally we thought that both bridges would have similar resistances.  Unfortunately the arch bridges design wasn’t able to hold more than 16lbs.  The arch design of the bridge was unable to hold more weight; the design had a flaw, which cause the bridge to bend vertically as weight was been added.  In the other hand the second bridge doubled the resistance of the arch bridge design.  This bridge didn’t show any visual disturbance or deformation in its structure while weight was been added.  The bridge collapsed after adding 32lbs of weight in a really weird way.  We were hoping the bridge medium structure to bend and break.  Instead it collapsed in a really weird place, the right side that was been supported by the stands broke. 
            Originally the WPBD programs provide us with numbers relating both the cost to resistance of the bridge.  This was really helpful because we were able to play and create different bridge designs and test their resistance and at the same time be able to know their cost.  Unfortunately we haven’t been able to find any equation that would help us calculate the numbers for the Knex bridge design.  The only thing that we are able to know from using the Knex is the cost of the bridge.  I think that it would be really helpful if there were an equation that could help use calculates the numbers related to the resistance of the bridges.  The only way possible to calculate the resistance of a Knex bridge is by actual testing.         

Week 7 - Analysis Desires

Last week during lab we had the task of testing our bridge design. We had two designs, one was unofficially tested and preformed better that the first one. The first design that was tested wasn't very successful because it depended on a arch structure that supported it self on the sides of the supports. this wasn't very reliable because the two saw horses aren't completely attached to the ground so when weight was added to the bridge the arch supports moved the supports to the sides as the weight went down, this first one only supported 16 lbs. Our second design was a much more typical truss bridge, so this didn't have the problem of moving the saw horses to the sides. This design supported around 32 lbs.
One of the things that will surely make our bridge design much better will be how we analyze the forces that act on each of the knex pieces. If we would know the stresses of each of the pieces we would be able to take out all the unnecessary pieces and include pieces that would help support more weight. The way I would approach this force analysis would be to take the different structures that make the bridge and simulate extreme forces that they would experience. For example I would take a simple two truss bridge and add weight to it until it failed, test various different setups and choose the most effective.

Wednesday, May 9, 2012

Week 6


Last week’s lab was really significant regarding the assembly of Knex bridges and decision-making.  We the preliminary and basic knowledge of using Knex, each member was able to assemble their own bridge design during the first part of the lab.  After each individual’s Knex was completed, the group came together again to discuss and analyze each of their bridges to be able to pick one.  Instead of simply picking one bridge, the team decided that it would be much better if they unified their ideas into one bridge and assemble it.  During next week’s lab the group is going to be able to test their bridge strength in a competition scenario.
            After been able to play around with the Knex more time, I wasn’t able to see any more limitations than the ones explained in the previous blog.  The same constraints that were mention appeared in the actual assemble of the bridge and they might affect the strength of the bridge.  Designing a real 20’ steel bridge is a completely different than building one with knex.  The design and assembly of the real bridge will be completely different and there would be new things that will need to be considered.  We would be able to overcome many of the constraints that were presented by the Knex and be able to build the bridge the way we want it to be.  Although we are going to be able to overcome many of the design constraints, many new things that need to be considered would arise.  We would need to completely make sure that the bridge design is going to be 100% successful in real life use.  We can’t afford it to fall apart after some time.  In order to assure its efficiency, we would have to consider many more facts rather than simply its design and strength.  For example we need to make sure that the structure will resist natural disasters like winds, earthquakes, climate, etc.   Also we need to think the material quality keeping in mind its cost.  We have to be able to reach an equilibrium between cost, durability and strength.  Building a real life bridge is much more complicated and involves more studying of the situation than assembling with Knex.