I believe that this term was very beneficial towards my major, it helped me consider different situations that I will eventually encounter in my academic as well as my professional career. This simple way of modeling bridges is an easy way of viewing one of the most basic ideas in engineering, trusses. These hollow structures are everywhere, from the crane that is building the new business building to the chair im sitting on. I think that by constantly experimenting with different structures I was able to better understand the forces that are constantly affecting a bridge. I think one of the least beneficial things of the course was the fact that we could only use a simple truss design. I would have enjoyed it if we were able to use arches and hanging bridge designs. This would have been a perfect introductory course on bridges and basics to civil and structural engineering. Other than that I think that this freshman design project was a good experience, I learned a lot about bridges and the way they can be built and can fail.
Tuesday, June 5, 2012
Week 10
Last week was the week where our final bridge designs were tested, the goal of the all the designs was to have the lowest cost to weight ratio. Our bridge won the competition with a ration of $8,542 per pound. The lab period was used for only the competition this upcoming lab period we'll have a closing discussion of what we did during the term.
A4-Weldon/Hidalgo/Almendariz
Bridge Report
Figure 1: Final bridge design. |
The bridge design competition is a lab module that tests different truss designs. The lab brings together computer modeling, physical modeling, forensic analysis, static analysis, and teamwork to build a bridge. The design process starts with computer modeling using programs like West Point Bridge Design and then the design process moves to physical modeling using Knex pieces to build the bridge you had earlier designed. The analysis tactics are used at certain intervals to help increase one’s understanding of how to build the bridge to its full potential. The main goal is to build a bridge with the lowest cost to weight held ratio.
Design Process
As we
started to build our final bridge design we started out by modeling it after
our first 24’’ design. It was a simple truss design with two levels of trusses
the top one shorter than the other. One
of our main goals was to replace the 360° grooved gusset plates with
alternatives that would eliminate the weakness created by the connections
between two of the gusset plates. With the help of the analysis of tensile pull
out forces of the Knex pieces we wanted to optimize the amount of force each of
the gusset plates experienced
(http://www.ce.memphis.edu/3121/projects/Project_1/fall_11/knex_pullout_force_f11.html).
As we continued to work on our design our first attempts were failures. We
tried several modifications one of them was to use the normal 360°
gusset plates buy connecting the members sideways rather than the conventional
way. This didn’t work as we planned because we didn’t consider it twisting
sideways which it did.
The role of the individual
projects such as West Point Bridge Design, Truss Analysis, and Individual Knex
Design is that each helped to bring different views and discovers to the group.
It allowed us to work off both what we discovered on our own and what others in
our group discovered. This made it so many ideas could be brought forth and
combined to make the best possible design. For example with the truss analysis
it quantified the specific forces that act on a bridge. This helped better our
design by purposefully orienting the direction of the grooved gusset plate
connections a direction that counteracted the forces acting on the bridge.
In choosing our final design we
decided to go two ways and combine them. The first one was to create a very
dense truss that was expected to be expensive but also that had a higher
resistance. The second was the original “arch” truss design, which had proven
to be effective in the first competition. The only component that was constantly
being modified was the under truss, this structure wasn’t a complete idea when
construction started it was more of an idea of how different gusset plates and
connectors could be combined. Eventually we came to the final design by using
the 360°
gusset plates in any way we could. The load at which we predicted the bridge to
fail was 40 lbs, we predicted this because of our previous experiences with the
bridges, our first bridge’s load at failure was about 30 lbs and since we used
the same set of pieces we didn’t expect our bridge to resist more than 40 lbs.
Final Design
Below is the plan view of our design the tilted rectangles and blue circles are 360° gusset plates, all the white circles are two 360° grooved gusset plates connected to each other.
In figure 3 a visual depiction is shown of how the gusset plate was used in the middle of the truss.
Our final Design was not very conventional because it included an intermediate truss which helped distribute the downwards force experienced by gravity. The truss helped resist more tension that is felt in the bottom part of any bridge. Below is a separate drawing of the truss that went in between the main structure.
Figure 5 and 6 are elevation views of our bridge. This particular view was challenging to draw because of the intricacy of the design.
Figure 3: Individual truss section |
Figure 4: Intermediate truss |
Figure 5: Elevation drawing |
Figure 6: Elevation view. |
Figure 7: Bill of Materials |
Testing Results
Our bridge was able to hold 102.6 lbs before failure occurred. The bridge failed at the gusset plates at the center of the bridge. The bridge split right down the middle. The failure was not caused by a member slipping out of a gusset plate as was observed earlier. Instead the plastic connector itself cracked from the force created by the weight. The crack of this one gusset plate caused the other gusset plates on the same plane to slide out. As Figures 8 and 9 show the split was right down the middle where most of the force was experienced.
Our bridge was able to hold 102.6 lbs before failure occurred. The bridge failed at the gusset plates at the center of the bridge. The bridge split right down the middle. The failure was not caused by a member slipping out of a gusset plate as was observed earlier. Instead the plastic connector itself cracked from the force created by the weight. The crack of this one gusset plate caused the other gusset plates on the same plane to slide out. As Figures 8 and 9 show the split was right down the middle where most of the force was experienced.
Figure 8: View of area that broke. |
Figure 9: Bridge after failure. |
Conclusions
The group’s
final bridge design model behaved completely different than expected. Originally we predicted the bridge to hold
about 40 pounds and not have a good cost to weight ratio. As stated previously the main focus when
designing the final bridge model was it’s strength. We decided to completely ignore the concern
of keeping its cost down and let our creativity focus on the structure and
strength of the bridge. We tried
dividing the weight resistance equally throughout the bridge to avoid putting excess tension on a single portion. This
way we were able to build a nonconventional bridge with an interesting
structure. Although we focused on the bridge
strength we underestimated its strength by hypothesizing that it wouldn't hold
more than 40 pounds. Our biggest concern
was the fact that the bridge had so many members and connections. We thought that connections would create weak
spots that would weaken the bridge. Therefore
we were expecting it to collapse by braking in the middle. During the competition the bridge had a
surprising behavior proving our hypothesis wrong. The bridge ended up being able to hold 102.6
pounds. Throughout the competition we
didn’t see any bending or twisting in the structure of the bridge. Although we were able to pull the biggest weight
resistance we didn’t expect it to be able to have a good cost to pound
ratio. By ignoring it’s cost during the
development of the design we ended surpassing all the other bridges cost by
pulling a cost of $826,500. Due to its
high cost we didn’t expect at all to be able to pull a reasonable cost to pound
ratio and predicted it to be $21,913. It
is for these reasons that we were surprised to know that our bridge won the
competition by pulling the best cost to pound ratio.
Future Work
Although
our bridge design model was successful and won the competition. If we were given the chance to modify and
improve we would make some changes to lower its cost. We would increase its scale by using bigger
members to create the same 36” and not modify its structure and shape at all.
This way we would use a less members and connectors reducing its cost
significantly and either keeping or improving its strength. We think that connections create weak points
in the bridge and by decreasing their number the bridge would strengthen the
bridge. Further more experimentations
and testing would need to be perform to see the effect of this change in its
strength. Also we misused 360 gusset
plates in the sides of the bottom level of the bridge. Figure 10 shows the inner design if the white gusset plates had been replaced by yellow 180 plates the cost would have been lowered significantly. We would not make major changes any changes
in the design and structure of the bridge model because we think its not
necessary.
Figure 10: View of bottom section before top is added. |
Figure 10: Cross section of bridge. |
Week 10
Week 10
In the
previous lab section we got the chance to test the group’s final bridge
model. All groups competed against each
other to try to attain the best cost to cost to pound ratio. Our group didn’t expect to win the
competition originally because we knew that our bridge was really expensive and
we didn’t predict it to hold more than 40 pounds of weight. It was shocking to first see that the bridge
was been able to hold so much weight and it wouldn’t collapse and best of to
see that we were able to pull the best ratio of all the class. Our bridge was able to pull up a cost to
pound ratio of $8542.88.
I found
this Engineering design project to be my favorite of all the year. I liked the way that the course was
structured throughout the whole term and dividing every assignment in a really
easy and effective time manner. This was
really helpful because it divided the workload in reasonable time amounts that
will not pill up everything for the last minute. I found all the material explored in this
course worthwhile and really interesting.
I think that the way that they were set and their structure were
essential for us to have a basic understanding of bridges and be able to design
one. Although I had some little
knowledge about bridges I did learn some really interesting and important material
through this course. I think that the
most significant piece of knowledge that I learn was by using WPBD. I found this program to be really
interesting an efficient by letting us know what work the best for
bridges. I was able to test different
bridge designs that I though about and was able to know which structure worked the
best. The least beneficial topic explored
was the one about teamwork because I think that teamwork skills are learning
through each experience. I don’t have
any significant suggestion for the improvement of this design project. I think that all of it was really well
structured and planned.
Monday, June 4, 2012
Bridge
This is the bridge that was used for the final competition.
Our bridge was constructed of 773 Knex pieces. The total cost reached $876,500.00. The bridge finally gave out at 102.6 lbs. Failure was dude to a gusset plate snapping. We believed that failure would occur at the center because this is where the weight is centered and this was the location of the broken gusset plate. The cost per weight ratio came to $8,542.88 per pound.
View of the cross section. |
View from the side. |
Sunday, June 3, 2012
Week 10
During last week's lab period we tested our final bridge design. The bridge was tested to how much weight could be held. The goal was to have the least cost per pound held. Our bridge had a ratio of $8,542.88 per pound.
In the upcoming week our team will have completed our A4 assignment. In lab we will go over an overview of what was done and taught during this term.
Major accomplishments for our group was that our bridge held the most weight and had the best cost to weight ratio.
I do not believe there are any issues facing the team now that the term is coming to a close.
Yes I do believe I learned something worthwhile about each of the topics for the course goals. I feel that I learned more on teamwork, which is very essential to the design process. I also learned a lot about planning, computer modeling, static analysis, and physical modeling. Each step took in the lab helped lead to the next and give us a better understanding of what we were designing and building.
I think that the static analysis was the least beneficial to this lab process. I believe this only because we are limited by the Knex pieces. Observing how angles affect the way the weight is distributed across the bridge is good knowledge to acquire, but does little to help with the design of our Knex bridge. If I showed X formations against other formations that could be designed with the Knex pieces it would be more helpful.
The most beneficial for me was the actual physical testing of the bridge. This was the most helpful because it brought together everything that was taught to you before that point. Also because it allowed you to see that a certain cross section between the two vertical sides had to be constructed or else the twisting would occur. Physical modeling and testing gave you the ability to fully view your bridge and see how added weight affected it.
My only suggestion is allow for more testing of the physical bridges before the final test.
By Robert Weldon
In the upcoming week our team will have completed our A4 assignment. In lab we will go over an overview of what was done and taught during this term.
Major accomplishments for our group was that our bridge held the most weight and had the best cost to weight ratio.
I do not believe there are any issues facing the team now that the term is coming to a close.
Yes I do believe I learned something worthwhile about each of the topics for the course goals. I feel that I learned more on teamwork, which is very essential to the design process. I also learned a lot about planning, computer modeling, static analysis, and physical modeling. Each step took in the lab helped lead to the next and give us a better understanding of what we were designing and building.
I think that the static analysis was the least beneficial to this lab process. I believe this only because we are limited by the Knex pieces. Observing how angles affect the way the weight is distributed across the bridge is good knowledge to acquire, but does little to help with the design of our Knex bridge. If I showed X formations against other formations that could be designed with the Knex pieces it would be more helpful.
The most beneficial for me was the actual physical testing of the bridge. This was the most helpful because it brought together everything that was taught to you before that point. Also because it allowed you to see that a certain cross section between the two vertical sides had to be constructed or else the twisting would occur. Physical modeling and testing gave you the ability to fully view your bridge and see how added weight affected it.
My only suggestion is allow for more testing of the physical bridges before the final test.
By Robert Weldon
Subscribe to:
Posts (Atom)